BIM Quantity Takeoff & Cost Estimator
Harbour Point Offices · Two-storey office building · sample estimate · Provisional: some lines unpriced
Net cost
£196,334
Waste allowance
£10,788
Subtotal
£207,122
Contingency 7.5%
£15,534
Estimated total
£222,656
Status
Provisional · 3 unpriced
Loading 3D model…
120 of 120 lines
| Unit | Rate | Status | ||||||
|---|---|---|---|---|---|---|---|---|
| TK-0001 | Concrete Slab 250 | Floors EL-1001 | Level 1 | 84 | m³ | £215.00/m³ | £18,060 | priced |
| TK-0002 | Floor finish to EL-1001 | Floors EL-1001 | Level 1 | 336 | m² | £55.00/m³ | — | unit mismatch |
| TK-0003 | Concrete 400×400 | Columns EL-1002 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0004 | Concrete 400×400 | Columns EL-1003 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0005 | Concrete 400×400 | Columns EL-1004 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0006 | Concrete 400×400 | Columns EL-1005 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0007 | Concrete 400×400 | Columns EL-1006 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0008 | Concrete 400×400 | Columns EL-1007 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0009 | Concrete 400×400 | Columns EL-1008 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0010 | Concrete 400×400 | Columns EL-1009 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0011 | Concrete 400×400 | Columns EL-1010 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0012 | Concrete 400×400 | Columns EL-1011 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0013 | Concrete 400×400 | Columns EL-1012 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
| TK-0014 | Concrete 400×400 | Columns EL-1013 | Level 1 | 0.512 | m³ | £480.00/m³ | £246 | priced |
Page 1 of 9
Quantities are derived from the sample model elements in your browser. Prices are invented illustrative rates. This is a preliminary demonstration and not a quotation, a verified takeoff or a project budget.